Lane Field North Hotel Development
Updated May 2014: Facts and dates to keep you informed
Lane Field parking: The existing lot will be divided in half. The North side will be developed according to the schedule details below. The South side is reserved for future development of a full service hotel which is currently unplanned. Until then, the South side will be remain a public parking lot.
Site size: 2.13 acres
Building: 18 stories; 185 feet above grade, 400 rooms.
Parking: Above ground for 400 cars; parking lot will be covered so cars will not be visible from above.
Art: Artwork will be commissioned along the parking structure wall facing Pacific Hwy.
Retail: There will 23,000 square feet of retail space.
Name: The hotel will be branded Marriott Springhill Suites and Residence Inn.
Setback: There will be a 150 setback park facing Harbor Drive (except for the Navy parking area).
The hotel entrance will be aligned with C Street and will be a court entered from Pacific Hwy. The Court will be right turn in from southbound Pacific Hwy and right turn out onto southbound Pacific Hwy. A traffic signal will be added after development of the south land field hotel.
CONSTRUCTION SCHEDULE
4/28/14 Construction Begins
5/14/14 South public parking lot reopens
7/18/14 Foundation complete
7/28/15 Structure complete
1/22/16 Construction complete
2/22/16 Hotel opens